A purchase order is on a job’s Cost Tracker, in the browser, for the job’s admins only. It holds one supplier to one agreed price on one job, and every invoice put against it is checked against what is left. A final invoice that is part purchase order and part extra, or that covers two orders, goes on as one invoice. Adding and checking the invoices themselves is on the Supplier Invoices help page.
Raising a purchase order: A purchase order is one supplier, one job and one agreed price before VAT, with their quotation attached. Once it is approved, the invoices put against it cannot take more than was agreed. Purchase orders are numbered across your company (PO-0001, PO-0002), so a supplier working on several of your jobs can put the number on their invoice. Each one is shown with its job’s code in front (STF-PO-0003 on a job whose code is STF), on your screens, on the page the supplier opens and in the email, so the number says which job it is for. Estimates, change orders and invoices to the client are named the same way (STF-EST-001, STF-CO-001, STF-INV-001). The code is the Project code in the job’s settings; change it there and the numbers follow from then on, while anything already sent keeps what it said.
- On the Cost Tracker, under Purchase orders, click New purchase order
- Choose the Supplier from your company’s contacts. A supplier not in your contacts has to be added first: an owner or admin of your company adds them under People, Add a contact
- Say what it is for, add the scope if you like, and type the Agreed price (£, before VAT)
- Choose a cost code if you use them, and drop in the supplier’s quotation. It is kept in a Purchase order quotes folder in Files that only the job’s admins can open
- Click Approve if you have agreed the price, or Save as draft to come back to it. No invoice can be put against a draft
Approving it yourself, and telling the supplier: Approve on a purchase order offers Email the supplier a copy, ticked whenever their contact has an email address. They get an email saying it is approved, with a link to read it and the number to put on their invoices. There is nothing for them to approve, and they do not need an account. Untick it to approve without emailing anyone. A purchase order you approved and never sent says Not sent to the supplier, on the Cost Tracker and on Orders under All projects. Click Send a copy on it to email them; Send a copy again is in its … menu once one has gone.
Sending a purchase order to the supplier to approve: Instead of approving it yourself, you can send it to the supplier, so you know they have seen it and agreed to it.
- On a draft purchase order, click Send to supplier
- Check Who at the supplier and Their email. They start from the supplier’s contact, or from whoever you sent it to last time
- Click Send. They get an email with the purchase order and a link. They do not need an account
On the link they read it (the number, what it is for, the scope, the agreed price before VAT and the job’s address), then either tick that they agree to supply it for that price and approve it, or decline it and say why if they like. The purchase order then shows who approved or declined it and when, with their reason. The email asks them to put the number on every invoice for the work.
While it is with the supplier it says With the supplier, no invoice can be put against it yet, and what it is for and its price cannot change. From its … menu you can Send again (the link in the last email stops working), Approve it yourself if you agree the price another way, or Take back to change it, which stops the link and makes it a draft again. A declined one can be taken back to change it and send it again, or cancelled.
If the email could not be sent, its link still works: the Cost Tracker gives it to you to send another way.
Once approved, a purchase order’s supplier, what it is for, its price and its scope are fixed. Its cost code and quotation can still change. If the supplier needs more money, agree it first, then choose Raise a variation from the purchase order’s … menu: a new purchase order for the extra, for the same supplier, marked as adding to the first. From the same menu, Close it when the work is finished, so no more invoices can go against it (Reopen undoes that). Cancel is for one nothing has been drawn from, and only a draft can be deleted.
Putting an invoice against a purchase order:
- On the invoice (adding it, or checking one under Invoices to check), choose it under Purchase order. Only approved ones are listed, the supplier’s own first, each saying what is left. If From is empty it is filled in with the purchase order’s supplier
- Put on PO-0001 starts at the invoice’s net. If the invoice is for more than is left, the form says so and offers Put £X on it
- Click Add invoice or Ready to pay
An invoice with extras, or on more than one purchase order: A supplier’s final invoice is often what is left of the purchase order plus something that was never on it, such as weekly scaffold inspections, or it covers the order and a variation raised as a second one.
- Put what the first purchase order takes in Put on PO-0001. The form says how much of the invoice is not on it
- For an extra, click Add a line for the £X (or Add a line not on a purchase order), and say What it is for. The amount starts at what is on nothing yet
- For a second purchase order, click Add another purchase order, choose it and type what it takes. Only the same supplier’s approved orders on this job are offered, and each is held to what is left on it
- How this invoice’s £X is split lists every part. The parts cannot come to more than the net; anything left over simply stays off every purchase order
It is still one invoice, with one cost code and one bill for your accounts. The Cost Tracker shows each extra purchase order and line beside it, and each purchase order counts what it took. To change them later, open the invoice.
An invoice cannot take a purchase order past its agreed price, or go against another supplier’s, another job’s, or a draft, closed or cancelled one: the Cost Tracker refuses it and says what is left. Day-rate labour needs no purchase order: leave Purchase order on No purchase order.
When Read the invoice finds your PO number printed on it, an approved purchase order of this job from that supplier is chosen by itself, and the form says so. Otherwise it says why, with Use PO-0012 where it could be used.
If the purchase order you need does not exist yet, click Raise one in a new tab and approve it there: back on the invoice it is in the list, and nothing you typed is lost.