A handover pack for a new build plot normally contains ten things: a contents page, the plot’s drawings at their current or as-built issue, the building control completion certificate, the warranty provider’s documents, the electrical and gas certificates, the energy performance certificate (EPC), test and commissioning records, appliance manuals and guarantees, the inspection and snag records, and photographs of work taken before it was covered up. It goes to the homeowner and the warranty provider, and sometimes to the solicitor. Warranty providers such as NHBC, LABC Warranty and Premier Guarantee each set their own requirements, so check yours before you rely on any general list, this one included.
If you build 5 to 40 plots a year with a few direct staff and everything else subbed out, you know how the pack gets made. Completion is a week away, and somebody in the office is searching email for the electrician’s certificate and scrolling the site manager’s camera roll for the cavity trays on Plot 7. The documents nearly always exist. They are in four places, and none of them says which plot it belongs to.
This guide gives the checklist first, then the habits that stop the pack being a last-week job. It describes general UK practice and is not legal advice. What your warranty provider, building control body and solicitor ask for on your scheme comes first.
What Goes in a Plot Handover Pack?
A plot handover pack is the set of documents showing what was built on one plot and that it was inspected and tested. The usual contents are:
A contents page. One page listing every document, so the reader can see what is there and what is not.
Drawings. The plot’s drawings at their current issue, or as-built drawings where the scheme calls for them: floor plans, elevations, drainage and the services layouts.
Building control completion certificate. Issued by the local authority or the registered building control approver once the final inspection is passed.
Warranty provider documents. The policy or cover documents for the plot and whatever sign-off your provider issues at the end of the build.
Electrical and gas certificates. The certificate for the electrical installation from the electrician, and the gas safety and commissioning paperwork from a Gas Safe registered engineer where the plot has gas.
The energy performance certificate (EPC). Produced for the finished home by the energy assessor.
Test and commissioning records. Whatever was tested or commissioned on the plot, such as heating, ventilation, air tightness, drainage, and smoke and heat alarms.
Appliance manuals and guarantees. The boiler or heat pump, the hob and oven, windows and doors, the garage door, and any installer guarantees for roofing, render or flooring.
Inspection and snag records. What was inspected at each stage and by whom, the snags raised, and which were closed before handover.
Photographs of work before it was covered up. Foundations, damp proof courses, insulation, fire stopping, and first fix pipework and cabling before the plasterboard went on.
Many developers add a home user guide at the front: how to run the heating and ventilation, where the stopcock and consumer unit are, what to expect as the house dries out, and who to call about a defect.
Who Does the Handover Pack Go To?
The pack has up to three readers, and they want different parts of it.
The homeowner wants the user guide, the manuals and guarantees, the certificates and the drawings. This is the copy people keep and hand on when they sell.
The warranty provider wants evidence that the home was built and inspected to its own standards. NHBC, LABC Warranty and Premier Guarantee each set their own requirements, so read yours at the start of the scheme, not the end.
The buyer’s solicitor sometimes asks for particular documents before completion. Your own solicitor will tell you what is being asked for on each sale.
Why Do Photographs Taken Before Plastering Matter?
Once the boards are on, a photograph is the only way to show what is behind them without cutting a hole. Insulation fitted tight between the studs, a cavity barrier in the right place, a pipe run clipped and lagged: all of it disappears behind the plasterboard.
These photographs earn their keep later. If a defect is reported two years on, the question is often whether something was fitted in the first place, and a dated photograph answers it.
A photograph is only evidence if you can say which plot it shows and when it was taken. It needs the plot’s name on it on the day, because nobody can tell Plot 6 from Plot 9 at first fix three months afterwards.
When Should You Start Collecting?
From the first day on the plot, not the last week. The pack takes days at the end because you are reconstructing it. In practice that means:
Photograph each stage before it is covered, on the day, and put it under the plot’s name straight away.
Ask each subbie for their certificate when they finish on the plot. An electrician who has just signed off Plot 4 can send it that afternoon. In the week of completion he is on another firm’s site.
Record inspections and snags against the plot as they happen, including the ones that passed first time.
How Should You Organise It by Plot?
Use the plot as the top level for everything, and use the same name everywhere. If the folder, the photograph album and the drawings are all marked “Plot 7”, anyone can pull the pack together. If the album is called “The Willow” and the drawings are filed under the house type, only the person who set it up can.
Inside each plot folder, mirror the checklist above. Keep site-wide documents, such as the drainage layout for the whole scheme, in one place, so there is one current version to update.
What Gaps Hold Up Completion?
The same few items are missing on plot after plot:
A certificate that was issued but never sent. The work was tested and nobody asked for the paperwork.
A certificate that does not name the plot. One sheet covering “Phase 2” is hard to file against a single house.
No photograph of a covered-up stage. The inspection happened, nothing was recorded, and the wall is now painted.
Superseded drawings. The pack holds revision B and the house was built to revision D.
Snags with no closing record. The list shows what was raised and not what was fixed. Our guide to snagging lists and snagging list template cover how to record a snag so it can be closed properly.
How Does BuildersAI Produce a Plot Handover Pack?
BuildersAI is the all-in-one site management app for UK builders, and its plot handover pack works on the same habit: mark things with the plot’s name as you go, and the pack is a download.
In the web app, open the project, go to Drawings, click Handover pack and choose the plot. You get one ZIP file to send to the homeowner or the warranty provider. It holds the plot’s drawings at their current issue, a page for each inspection and each snag, the plot’s photographs, and the documents in the plot’s folder. An index.html file lists everything with a link to each file and prints as the contents page.
✓Nothing new to fill in. The pack gathers what already carries the plot’s name: the task named after the plot and everything under it, anything with the plot’s label, the drawings tagged with it, and the album and the folder named for it.
✓It says what it could not find. If there is no album or no folder for the plot, the box tells you before you produce the pack, and the index says so in plain words.
✓Private items are left out. The index says how many, and the same goes for anything above your own access level.
✓Honest about names. Each record page shows who marked the item complete and when, and says that the name is the account that made the change, not a signature.
✓A record of each pack. BuildersAI keeps a record of who produced each pack, for which plot and when.
✓Part L photos as you go. Each plot’s album can carry the photographs Approved Document L asks for, with a warning the working day before a detail is covered up, so the pack is not missing the one picture building control wants. See Part L photos.
Two limits are worth knowing. The pack is a copy of your project record. It is not a warranty or a certificate, and it says so on its first page, so certificates still come from the people who issue them and go into the plot’s folder. And it is made in a browser by admins and members, not on the phone.
The step by step is in the handover pack page and its help page. If you only need photographs with their dates and locations, an evidence pack does that on its own. For how the rest of the app suits a developer running several plots, see property developer software.
FAQ
What goes in a handover pack for a new build?
A contents page, the plot’s current or as-built drawings, the building control completion certificate, the warranty provider’s documents, electrical and gas certificates, the EPC, test and commissioning records, appliance manuals and guarantees, inspection and snag records, and photographs of work before it was covered up.
Is there a standard handover pack template for new builds in the UK?
Not a single one. Warranty providers such as NHBC, LABC Warranty and Premier Guarantee each set their own requirements, and the buyer’s solicitor may ask for particular documents. Use a general checklist as a starting point, then check it against what your own provider asks for.
What is a home user guide for a new build?
A plain-English guide for the person living in the house: how to run the heating, hot water and ventilation, where the stopcock, meters and consumer unit are, what to expect while the house dries out, and who to contact about a defect. It usually sits at the front of the homeowner’s copy of the pack.
Does the BuildersAI handover pack replace the certificates?
No. It is a copy of the project record for one plot. It is not a warranty, a certificate or a signature. Certificates still come from whoever issues them, and you file them in the plot’s folder so they are included in the pack.
How much does BuildersAI cost?
There is a 14-day free trial with no card needed. After that it is a flat monthly price with no per-user fees: Starter is £149 a month for up to 10 users, Professional is £299 for 11 to 50, and Business is £599 for 51 to 100. Prices exclude VAT. The full detail is on the pricing page.
See a Plot Handover Pack Produced
We will show you a handover pack being produced for one plot, and what your own plots would need marked up to get the same.
William grew up in a family that builds houses for a living and has been around construction sites for as long as he can remember. He has seen first hand that eight-figure sites are often run on WhatsApp and spreadsheets, and started BuildersAI to cut the invisible costs that take chunks of margin across a site. His aim is for BuildersAI to be the all-in-one site management platform built in the UK, for UK sites.
Every failed snagging list fails the same way: vague descriptions, no owner, no deadline, no evidence. Here is a template that fixes all four, with a worked example you can copy this afternoon.
Most UK property developers manage multiple sites with a combination of WhatsApp, phone calls, and spreadsheets. It works until it doesn't. This article covers what breaks, what good software looks like, and what to look for when choosing a platform.
98% of new UK homes have defects at handover, averaging 100+ snags per dwelling. Learn how to create effective snagging lists, conduct inspections, and reduce callbacks.
15 min read
Get started
Ready to bring your whole team onto
one simple app?
14-day free trial with every feature, no card and no contract, and your team can be set up
within a day.